Exam 12: Resource Planning
Exam 1: Creating Customer Value through Operations128 Questions
Exam 2: Supply Chain Management171 Questions
Exam 3: Process Configuration137 Questions
Exam 4: Capacity145 Questions
Exam 5: Inventory Management177 Questions
Exam 6: Quality and Process Improvement240 Questions
Exam 7: Lean Systems158 Questions
Exam 8: Managing Projects153 Questions
Exam 9: Location and Layout217 Questions
Exam 10: Managing Demand and Forecasting189 Questions
Exam 11: Operations Planning and Scheduling138 Questions
Exam 12: Resource Planning174 Questions
Exam 13: Decision Making82 Questions
Exam 14: Financial Analysis41 Questions
Exam 15: Work Measurement98 Questions
Exam 16: Learning Curve Analysis44 Questions
Exam 17: Computer-Integrated Manufacturing53 Questions
Exam 18: Acceptance Sampling Plans71 Questions
Exam 19: Simulation36 Questions
Exam 20: Special Inventory Models33 Questions
Exam 21: Linear Programming57 Questions
Exam 22: Waiting Lines109 Questions
Select questions type
Table 13.8
Sunshine Manufacture produces three products, X, Y, and Z. The production of these end items is controlled by an MRP system. Each end item X is assembled with two components of A and one component of B. Each end item of Y is assembled with two components of C and one component of A, each component of C is manufactured from one unit of B. End item Z is assembled from one unit of D and one unit of C, D is manufactured from one unit of A, and C is manufactured from one unit of B.
-Use the information in Table 13.8.If level-by-level processing is used,what is a correct order for processing components A,B,C,and D?
(Multiple Choice)
4.8/5
(45)
An intermediate item must have a least one components and least one parent.
(True/False)
4.8/5
(38)
Part commonality refers to a degree to which a component has more than one immediate parent.
(True/False)
4.8/5
(35)
Table 13.7
-Use the information from Table 13.7.If a POQ lot-sizing rule is used,where P = 3,how many planned order releases are there for item XYZ?

(Multiple Choice)
4.8/5
(32)
The ________ is a record that divides the future into time periods called time buckets.
(Short Answer)
4.9/5
(42)
An enterprise process is a company-wide process that cuts across functional areas,business units,geographic regions,and product lines.
(True/False)
4.8/5
(40)
Table 13.7
-Use the information from Table 13.7.If a FOQ of 100 units is used,how many planned order releases are there for item XYZ?

(Multiple Choice)
4.9/5
(36)
The aggregate plan,derived from the master production schedule,specifies in more detail how much which products is to be made and at what times.
(True/False)
4.7/5
(45)
A periodic order quantity issues orders at predetermined intervals using the same quantity for each order.
(True/False)
4.7/5
(35)
Table 13.8
Sunshine Manufacture produces three products, X, Y, and Z. The production of these end items is controlled by an MRP system. Each end item X is assembled with two components of A and one component of B. Each end item of Y is assembled with two components of C and one component of A, each component of C is manufactured from one unit of B. End item Z is assembled from one unit of D and one unit of C, D is manufactured from one unit of A, and C is manufactured from one unit of B.
-Use the information in Table 13.8.If item C has a manufacturing lead time of two weeks and a planned receipt of 65 units is needed in week 4,which of the following statements is TRUE?
(Multiple Choice)
4.9/5
(32)
Part commonality refers to the degree to which a component has more than one immediate parent.
(True/False)
4.8/5
(43)
Use the following MRP record to answer the question.
What are the quantities of planned order releases for item XYZ for the first six weeks (weeks 1,2,3,4,5,and 6)?

(Multiple Choice)
4.9/5
(38)
An item made from water more components is referred to as a parent item.
(True/False)
4.8/5
(37)
One of the differences between Enterprise Resource Planning (ERP)and MRPII is that
(Multiple Choice)
4.9/5
(36)
A material requirements plan for each component item is generated from the master production schedule and other sources using an MRP explosion.
(True/False)
4.7/5
(38)
Table 13.1
-Use the following MRP record to answer the question.
What are the quantity and the week of the first planned order release?


(Multiple Choice)
4.8/5
(34)
The lot-sizing rule that generates the highest level of average inventory because it creates inventory remnants is
(Multiple Choice)
4.8/5
(34)
Table 13.5
-Use the following MRP record to answer the question.
Which one of the statements concerning item LMN is TRUE?


(Multiple Choice)
4.9/5
(46)
Showing 41 - 60 of 174
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)