Exam 12: Resource Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Planned lead time for purchased items is

(Multiple Choice)
4.8/5
(35)

Which of the following statements about MRP II is TRUE?

(Multiple Choice)
5.0/5
(43)

Table 13.7 Table 13.7    -Use the information from Table 13.7.Which lot sizing rule results in the highest average inventory? -Use the information from Table 13.7.Which lot sizing rule results in the highest average inventory?

(Multiple Choice)
4.8/5
(37)

The master production schedule is part of the material requirements plan that specifies how many end items will be produced within specified periods of time.

(True/False)
5.0/5
(28)

________ is an algorithm designed to schedule a group of orders appropriately across an entire shop.

(Short Answer)
4.8/5
(39)

Which one of the following statements about lot-sizing rules is TRUE?

(Multiple Choice)
4.8/5
(40)

In MRP,the inventory record divides the future into time periods called time baskets.

(True/False)
4.9/5
(45)

Table 13.4 Consider the MPS, BOM and inventory data shown below. Master Production Schedule: the following table shows the MPS start quantities. Week Week 1 2 3 4 5 6 MPS 80 80 Bill of Material -Item A uses 1 each of component D, 2 each of component C and 2 each of subassembly B. -Subassembly B uses 1 each of component D. Selected Inventory Data Item Data Category B Lot-sizing rule LAL OQ=180 (=2) Lead time (wks) 1 1 2 Beginning (on-hand) 30 160 50 inventory 190 (wk 2) 180( wk 11) 80( wk 1) Scheduled receipts -Use the information in Table 13.4.When does the first planned order release for item C occur?

(Multiple Choice)
4.8/5
(41)

Which one of the following is an MRP lot-sizing rule that attempts to minimize the amount of average inventory?

(Multiple Choice)
4.9/5
(37)

The ________ rule is a special case of the periodic order quantity (POQ)rule where the lot size ordered covers the gross requirements of a single time period (e.g.one week).

(Short Answer)
4.8/5
(31)

Julius testing: Dependent demand occurs because the quantity required is a function of the demand for other items held in inventory.

(True/False)
4.8/5
(39)

One of the three types of MRP action notices possible is releasing a new order.Which one of the following statements is TRUE about releasing a new order?

(Multiple Choice)
4.8/5
(35)

________ are orders that have not yet been released to the shop or the supplier.

(Short Answer)
4.8/5
(46)

Complete the following MRP schedule: Complete the following MRP schedule:

(Essay)
4.8/5
(33)

Table 13.7 Table 13.7    -Use the information from Table 13.7.If a L4L lot-sizing rule is used,how many planned order releases are there for item XYZ? -Use the information from Table 13.7.If a L4L lot-sizing rule is used,how many planned order releases are there for item XYZ?

(Multiple Choice)
4.9/5
(30)

Use the following MRP record to answer the following question. Use the following MRP record to answer the following question.   What is the planned order release quantity in week 4? What is the planned order release quantity in week 4?

(Multiple Choice)
4.9/5
(37)

________ is a lot-sizing rule that maintains the same order quantity each time an order is issued.

(Short Answer)
4.8/5
(41)

A(n)________ item is the final product sold to a customer.

(Short Answer)
4.7/5
(41)

Which one of the following statements about MRP is best?

(Multiple Choice)
4.9/5
(41)

Complete the following MRP schedule: Complete the following MRP schedule:

(Essay)
4.8/5
(45)
Showing 21 - 40 of 174
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)