Exam 12: Resource Planning
Exam 1: Creating Customer Value through Operations128 Questions
Exam 2: Supply Chain Management171 Questions
Exam 3: Process Configuration137 Questions
Exam 4: Capacity145 Questions
Exam 5: Inventory Management177 Questions
Exam 6: Quality and Process Improvement240 Questions
Exam 7: Lean Systems158 Questions
Exam 8: Managing Projects153 Questions
Exam 9: Location and Layout217 Questions
Exam 10: Managing Demand and Forecasting189 Questions
Exam 11: Operations Planning and Scheduling138 Questions
Exam 12: Resource Planning174 Questions
Exam 13: Decision Making82 Questions
Exam 14: Financial Analysis41 Questions
Exam 15: Work Measurement98 Questions
Exam 16: Learning Curve Analysis44 Questions
Exam 17: Computer-Integrated Manufacturing53 Questions
Exam 18: Acceptance Sampling Plans71 Questions
Exam 19: Simulation36 Questions
Exam 20: Special Inventory Models33 Questions
Exam 21: Linear Programming57 Questions
Exam 22: Waiting Lines109 Questions
Select questions type
The bill of resources (BOR)is a record of all the required material,equipment time,staff,and other resources needed,the parent-component relationships,and the usage quantities.
(True/False)
4.8/5
(37)
Table 13.5
-Use the information in Table 13.5.Which one of the statements concerning item RST is TRUE?

(Multiple Choice)
4.7/5
(38)
________ are the total demand derived from all parent production plans.
(Short Answer)
4.8/5
(37)
Which one of the following statements concerning MRP is TRUE?
(Multiple Choice)
4.7/5
(40)
Lumpy dependent demand can result from continuous independent demand.
(True/False)
4.9/5
(39)
Table 13.7
-Management wishes to use a FOQ lot-sizing rule for an item based on the economic order quantity.If the annual demand is 1200 units,the holding cost is $10/unit/year,and the setup cost is $50/lot,which one of the following fixed order quantities is most appropriate?

(Multiple Choice)
4.8/5
(36)
________ is a technique used for projecting time-phased capacity requirements for workstations.
(Short Answer)
4.8/5
(42)
Which one of the following is a feature of MRP II,but not available in basic MRP systems?
(Multiple Choice)
4.7/5
(37)
Consider the MPS,BOM,and inventory data shown below.
Master Production Schedule: the following table shows the MPS start quantities.
Finished Item A 1 2 3 4 5 6 7 8 Finished Item A MPS Start 20 40 30 20 40
Bill of Material:
- Item A uses 2 each of component D,1 each of component C and 2 each of subassembly B.
- Subassembly B uses 2 each of component E.
Selected Inventory Data:
Item Lot Size Technique Lead Time Scheduled Receipts On-Hand A 1 40 in period 1 =3 2 40 =250 1 160 in period 100 A 2 2
Construct the MRP schedule using the above information.
(Essay)
4.8/5
(31)
Table 13.6
-Complete the following MRP record in order to answer the question.
How many action notices will there be for item XYZ?


(Multiple Choice)
4.8/5
(33)
The quantity required of a dependent demanded item is computed from the demand for the final products in which the item is used.
(True/False)
4.8/5
(30)
Explain the key differences between the FOQ,POQ and L4L lot sizing rules.
(Essay)
4.7/5
(34)
Finite capacity scheduling is an algorithm designed to schedule a group of orders appropriately across the entire shop.
(True/False)
5.0/5
(40)
Use the following MRP record to answer the question.
How large is the second planned order release?

(Multiple Choice)
4.9/5
(40)
ERP systems allow an organization to view its operations as functional areas rather than having to try to put together the different information pieces produced by its various functions and divisions.
(True/False)
4.8/5
(27)
Table 13.3
Consider the following MPS, BOM, and inventory data. You will need a blank MRP record to answer the question(s).
Master Production Schedule: the following table shows the MPS start quantities.
Week
Week 1 2 3 4 5 6 A 50 80 100 B 60 100
Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
Item
Data Category Lot-sizing rule A A =250 POQ (P = Lead time (wks) 3 1 3 2) Beginning (on-hand) 50 80 90 1 inventory 80( wk 1) None 250( wk 3) 30 Scheduled receipts wk 1)
-Use the information in Table 13.3.Which one of the following statements on item C is TRUE?
(Multiple Choice)