Exam 12: Resource Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The bill of resources (BOR)is a record of all the required material,equipment time,staff,and other resources needed,the parent-component relationships,and the usage quantities.

(True/False)
4.8/5
(37)

Table 13.5 Table 13.5    -Use the information in Table 13.5.Which one of the statements concerning item RST is TRUE? -Use the information in Table 13.5.Which one of the statements concerning item RST is TRUE?

(Multiple Choice)
4.7/5
(38)

________ are the total demand derived from all parent production plans.

(Short Answer)
4.8/5
(37)

Which one of the following statements concerning MRP is TRUE?

(Multiple Choice)
4.7/5
(40)

Lumpy dependent demand can result from continuous independent demand.

(True/False)
4.9/5
(39)

Table 13.7 Table 13.7    -Management wishes to use a FOQ lot-sizing rule for an item based on the economic order quantity.If the annual demand is 1200 units,the holding cost is $10/unit/year,and the setup cost is $50/lot,which one of the following fixed order quantities is most appropriate? -Management wishes to use a FOQ lot-sizing rule for an item based on the economic order quantity.If the annual demand is 1200 units,the holding cost is $10/unit/year,and the setup cost is $50/lot,which one of the following fixed order quantities is most appropriate?

(Multiple Choice)
4.8/5
(36)

Discuss the master production schedule.

(Essay)
4.9/5
(36)

________ is a technique used for projecting time-phased capacity requirements for workstations.

(Short Answer)
4.8/5
(42)

Which one of the following is a feature of MRP II,but not available in basic MRP systems?

(Multiple Choice)
4.7/5
(37)

Part commonality tends to increase inventory costs.

(True/False)
4.8/5
(31)

Consider the MPS,BOM,and inventory data shown below. Master Production Schedule: the following table shows the MPS start quantities. Finished Item A 1 2 3 4 5 6 7 8 Finished Item A MPS Start 20 40 30 20 40 Bill of Material: - Item A uses 2 each of component D,1 each of component C and 2 each of subassembly B. - Subassembly B uses 2 each of component E. Selected Inventory Data: Item Lot Size Technique Lead Time Scheduled Receipts On-Hand A 1 40 in period 1 =3 2 40 =250 1 160 in period 100 A 2 2 Construct the MRP schedule using the above information.

(Essay)
4.8/5
(31)

What is a bill of materials? Discuss.

(Essay)
4.9/5
(41)

Table 13.6 Table 13.6    -Complete the following MRP record in order to answer the question.   How many action notices will there be for item XYZ? -Complete the following MRP record in order to answer the question. Table 13.6    -Complete the following MRP record in order to answer the question.   How many action notices will there be for item XYZ? How many action notices will there be for item XYZ?

(Multiple Choice)
4.8/5
(33)

Which of the following statements about MRP is TRUE?

(Multiple Choice)
4.8/5
(27)

The quantity required of a dependent demanded item is computed from the demand for the final products in which the item is used.

(True/False)
4.8/5
(30)

Explain the key differences between the FOQ,POQ and L4L lot sizing rules.

(Essay)
4.7/5
(34)

Finite capacity scheduling is an algorithm designed to schedule a group of orders appropriately across the entire shop.

(True/False)
5.0/5
(40)

Use the following MRP record to answer the question. Use the following MRP record to answer the question.   How large is the second planned order release? How large is the second planned order release?

(Multiple Choice)
4.9/5
(40)

ERP systems allow an organization to view its operations as functional areas rather than having to try to put together the different information pieces produced by its various functions and divisions.

(True/False)
4.8/5
(27)

Table 13.3 Consider the following MPS, BOM, and inventory data. You will need a blank MRP record to answer the question(s). Master Production Schedule: the following table shows the MPS start quantities. Week Week 1 2 3 4 5 6 A 50 80 100 B 60 100 Bill of Material -End item A uses 1 each of component C and 1 each of subassembly D. -Subassembly D uses 2 each of component E and 2 each of component F. -End item B uses 1 each of component C and 2 each of component F. Selected Inventory Data Item Data Category Lot-sizing rule A A =250 POQ (P = Lead time (wks) 3 1 3 2) Beginning (on-hand) 50 80 90 1 inventory 80( wk 1) None 250( wk 3) 30 Scheduled receipts wk 1) -Use the information in Table 13.3.Which one of the following statements on item C is TRUE?

(Multiple Choice)
5.0/5
(33)
Showing 61 - 80 of 174
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)