Exam 2: Process Strategy and Analysis
Exam 1: Using Operations to Create Value115 Questions
Exam 2: Process Strategy and Analysis239 Questions
Exam 3: Quality and Performance198 Questions
Exam 4: Capacity Planning120 Questions
Exam 5: Constraint Management136 Questions
Exam 6: Lean Systems166 Questions
Exam 7: Project Management139 Questions
Exam 8: Forecasting150 Questions
Exam 9: Inventory Management205 Questions
Exam 10: Operations Planning and Scheduling149 Questions
Exam 11: Resource Planning124 Questions
Exam 12: Supply Chain Design77 Questions
Exam 13: Supply Chain Logistic Networks114 Questions
Exam 14: Supply Chain Integration120 Questions
Exam 15: Supply Chain Sustainability78 Questions
Exam 16: Supplement A Decision Making107 Questions
Exam 17: Supplement J Operations Scheduling123 Questions
Exam 18: Supplement K Layout39 Questions
Exam 19: Supplement B Waiting Lines111 Questions
Exam 20: Supplement C Special Inventory Models53 Questions
Exam 21: Supplement D Linear Programming87 Questions
Exam 22: Supplement E Simulation54 Questions
Exam 23: Supplement F Financial Analysis55 Questions
Exam 24: Supplement G Acceptance Sampling Plans87 Questions
Exam 25: Supplement H Measuring Output Rates108 Questions
Exam 26: Supplement I Learning Curve Analysis50 Questions
Select questions type
Which one of the following statements concerning the role of process reengineering is best?
(Multiple Choice)
4.8/5
(41)
Scenario 2.5
A job consists of three distinct work elements that were timed with a highly accurate Swiss watch by a trained industrial engineer. The engineer recorded ten observations listed in the following table. All recorded times are in seconds.
-Use the data in Scenario 2.5 to answer this question. If the performance rating factor is 15%, what is the average time for Element 1?

(Multiple Choice)
4.8/5
(37)
Scenario 2.5
A job consists of three distinct work elements that were timed with a highly accurate Swiss watch by a trained industrial engineer. The engineer recorded ten observations listed in the following table. All recorded times are in seconds.
-Use the data in Scenario 2.5 to answer this question. If the rating factor is 1.15, what is the normal time for Element 3?

(Multiple Choice)
4.7/5
(37)
Explain why a sampling schedule is important in a work sampling study.
(Essay)
4.9/5
(39)
A moment of truth or service encounter is face-to-face interaction between the customer and a service provider.
(True/False)
4.8/5
(31)
In a swim lane flowchart, the line of visibility is used to separate the process steps in view of the customer from those hidden from view of the customer.
(True/False)
4.9/5
(35)
Active customer contact and personalized attention can lower cost to the customer by:
(Multiple Choice)
4.8/5
(38)
Scenario 2.4
A company is considering two options for the production of a part needed downstream in the manufacturing process. Particulars are as follows:
-Use Scenario 2.4 to solve this problem. What does the company save each month by selecting this low-cost option compared to the higher-cost option (for monthly requirements of 3,000 units)?

(Multiple Choice)
4.8/5
(32)
________ are performance measures that are established for a process and the steps within it.
(Short Answer)
4.8/5
(38)
Scenario 2.6
You currently purchase a part used in your production process from an outside supplier, and have decided to begin making this part in-house. You have two equipment options for moving production in-house: special-purpose equipment and general-purpose equipment. Cost information for these two options is as follows:
-Use Scenario 2.6 to solve this mystery. At an annual requirement of 40,000 units, what does the company save per year by selecting the lower-cost option?

(Multiple Choice)
4.8/5
(37)
Garman observes a worker assembling peanut valves and records the data displayed in the table. What is the normal time for this job element if the worker is rated at 80%? 

(Multiple Choice)
4.7/5
(38)
A time study analyst is attempting to determine the standard time for a work element. She observes a worker performing the work element at a higher-than-average pace. How will this fact be reflected in the time standard that is eventually created?
(Multiple Choice)
4.9/5
(33)
Divergence is the extent to which the process is customized with considerable latitude on how the tasks are performed.
(True/False)
4.7/5
(34)
Scenario 2.4
A company is considering two options for the production of a part needed downstream in the manufacturing process. Particulars are as follows:
-Use Scenario 2.4 to answer this burning question. For a monthly volume of 3,000 units, which automation approach should be chosen?

(Multiple Choice)
4.9/5
(41)
The ________ in a service blueprint separates which steps are in view of the customer from those that aren't.
(Short Answer)
4.9/5
(36)
Which of these tools is considered a primary enabler of process reengineering?
(Multiple Choice)
4.9/5
(36)
Scenario 2.2
Garman observes a worker assembling peanut valves and records the data displayed in the table.
-Use the information in Scenario 2.2. What is the average time for this job element?

(Multiple Choice)
4.9/5
(37)
Xerox benchmarked its distribution system against that of L. L. Bean's. This is an example of:
(Multiple Choice)
4.7/5
(33)
Showing 61 - 80 of 239