The inability to get more than two earth movers on a construction site at the same time is an example of a physical constraint.

(True/False)
4.8/5
(26)

The ability to more efficiently manage the ebbs and flows of project work is one of the major driving forces behind ____________ today.

(Short Answer)
4.8/5
(31)

In order that the new product is on the shelf for the Christmas buying season, the development of the new product would be classified as a(n) ________ constrained project.

(Short Answer)
4.8/5
(35)

A shortage of programmers to write software is an example of a(n) ________ type of resource constraint.

(Short Answer)
4.9/5
(33)

Splitting an activity creates the following situation:

(Multiple Choice)
4.8/5
(36)

To deal with problems related to having several concurrent projects, companies are creating ________ to oversee the scheduling of resources across multiple projects.

(Short Answer)
4.9/5
(27)

Describe the parallel method for applying heuristics to the allocation of project resources.

(Essay)
4.7/5
(26)

In scheduling resource-constrained projects, _________ are typically used rather than optimum mathematical solutions.

(Short Answer)
4.8/5
(37)

Identify and briefly discuss the three more common problems encountered in managing multiproject resource schedules.

(Essay)
4.8/5
(37)

When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called

(Multiple Choice)
4.9/5
(32)

If a project needs one earth-mover six months from now and the organization has four such machines, there is no equipment resource constraint.

(True/False)
4.9/5
(43)

The U.S.Forest Service "snapshot from practice" illustrated the importance of

(Multiple Choice)
4.9/5
(33)

The ______________ is the most widely used approach to apply heuristics in resource-constrained projects.

(Short Answer)
4.9/5
(34)

Identify and briefly describe the two classifications of scheduling problems.

(Essay)
4.8/5
(38)

A lack of readily available engineers is a technical constraint.

(True/False)
4.9/5
(30)

The shortage of computer chips to produce a circuit board is an example of a(n) ________ type of resource constraint.

(Short Answer)
4.8/5
(33)

Having too few programmers and too many engineers is an example of a people resource constraint.

(True/False)
4.8/5
(37)

Scheduling time-constrained projects focuses on the optimal utilization of resources.

(True/False)
4.8/5
(27)

In a resource-constrained project the third priority in assigning resources is usually given to activities with the

(Multiple Choice)
4.8/5
(26)

More common problems associated with managing multiproject resources include all of the following except

(Multiple Choice)
4.8/5
(31)