Exam 3: Managing Projects
Exam 1: Operations and Productivity127 Questions
Exam 2: The Global Environment and Operations Strategy119 Questions
Exam 3: Managing Projects120 Questions
Exam 4: Forecasting Demand140 Questions
Exam 5: Product Design118 Questions
Exam 6: Quality Management and International Standards123 Questions
Exam 7: Process Design108 Questions
Exam 8: Location Decisions121 Questions
Exam 9: Layout Decisions146 Questions
Exam 10: Job Design and Work Measurement154 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Managing Inventory163 Questions
Exam 13: Aggregate Scheduling116 Questions
Exam 14: Material Requirements Planning Mrpand Erp113 Questions
Exam 15: Scheduling for the Short-Term116 Questions
Exam 16: Jit,lean Operations,and the Toyota Production System115 Questions
Exam 17: Maintenance and Reliability Decisions111 Questions
Exam 18: Sustainability80 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity Planning96 Questions
Exam 21: Supply Chain Modeling55 Questions
Exam 22: Decision Modeling97 Questions
Exam 23: Linear Programming Models88 Questions
Exam 24: Transportation Modeling89 Questions
Exam 25: Queuing Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Modeling with Simulation75 Questions
Select questions type
Which of the following statements regarding PERT analysis is true?
(Multiple Choice)
4.8/5
(37)
Draw the AOA and AON networks for the following project and calculate the minimum project duration.


(Essay)
4.8/5
(33)
The ________ is a project management technique using only one time factor per activity that enables managers to schedule,monitor,and control large and complex projects.
(Essay)
4.9/5
(49)
If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000,what is the crash cost per period?
(Multiple Choice)
4.9/5
(37)
The time an activity will take assuming very unfavorable conditions is:
(Multiple Choice)
4.8/5
(36)
Slack is the amount of time an activity can be delayed without delaying the entire project.
(True/False)
4.8/5
(32)
The control of projects involves close monitoring of which of the following?
(Multiple Choice)
4.9/5
(40)
Shortening the project's duration by deleting unnecessary activities is called "project crashing."
(True/False)
4.8/5
(38)
In project management,crashing an activity must consider the impact on all paths in the network.
(True/False)
4.8/5
(36)
Ethical issues that can arise in projects include gifts from contractors,pressure to mask delays with false status reports,and pressure to compromise project quality to meet bonuses or avoid penalties related to schedules.
(True/False)
4.8/5
(37)
________ is the amount of time an individual activity in a network can be delayed without delaying the entire project.
(Essay)
4.8/5
(35)
Consider the network presented in the following table.Calculate
a.All possible paths
b.The critical path
c.The slack available at any non-critical points
d.The minimum project duration


(Essay)
4.8/5
(30)
The ________ distribution is appropriate for calculating expected activity times and activity variances in PERT networks.
(Essay)
4.8/5
(26)
Match the following steps in Microsoft's development of Windows 8 to their respective WBS level. Step Level
Develop Windows 8 Operating System ?
System Testing ?
Compatible with Windows 7 ?
Develop GUI's ?
Module Testing ?
(Multiple Choice)
5.0/5
(34)
Given the critical path below,calculate the following:
a.The crash cost per unit time savings for each activity.
b.The maximum total crash time savings and cost.
c.The maximum total time-savings with a $3000 budget.


(Essay)
4.9/5
(34)
The critical path for the network activities shown below is ________ with duration ________. 

(Multiple Choice)
4.8/5
(46)