Exam 3: Managing Projects
Exam 1: Operations and Productivity127 Questions
Exam 2: The Global Environment and Operations Strategy119 Questions
Exam 3: Managing Projects120 Questions
Exam 4: Forecasting Demand140 Questions
Exam 5: Product Design118 Questions
Exam 6: Quality Management and International Standards123 Questions
Exam 7: Process Design108 Questions
Exam 8: Location Decisions121 Questions
Exam 9: Layout Decisions146 Questions
Exam 10: Job Design and Work Measurement154 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Managing Inventory163 Questions
Exam 13: Aggregate Scheduling116 Questions
Exam 14: Material Requirements Planning Mrpand Erp113 Questions
Exam 15: Scheduling for the Short-Term116 Questions
Exam 16: Jit,lean Operations,and the Toyota Production System115 Questions
Exam 17: Maintenance and Reliability Decisions111 Questions
Exam 18: Sustainability80 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity Planning96 Questions
Exam 21: Supply Chain Modeling55 Questions
Exam 22: Decision Modeling97 Questions
Exam 23: Linear Programming Models88 Questions
Exam 24: Transportation Modeling89 Questions
Exam 25: Queuing Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Modeling with Simulation75 Questions
Select questions type
In PERT analysis,the identification of the critical path can be incorrect if a noncritical activity takes substantially more than its expected time.
(True/False)
4.9/5
(40)
The critical path can be determined by use of either the "forward pass" or the "backward pass."
(True/False)
4.8/5
(33)
In a PERT network,non-critical activities that have little slack need to be monitored closely:
(Multiple Choice)
4.9/5
(40)
How is the expected completion time of a project activity,and of a PERT project,computed?
(Essay)
4.9/5
(32)
The network below represents a project being analyzed by the critical path method.Activity durations are indicated on the network.
a.Identify the activities on the critical path.
b.What is the duration of the critical path?
c.Calculate the amount of slack time at activity H.
d.If activity I were delayed by ten time units,what would be the impact on the project duration?

(Essay)
4.8/5
(36)
Consider the network described in the table below.
a.Calculate the expected duration of each activity.
b.Calculate the expected duration and variance of the critical path.
c.Calculate the probability that the project will be completed in fewer than 30 time units.

(Essay)
4.9/5
(29)
A contractor's project being analyzed by PERT has an estimated time for the critical path of 120 days.The sum of all activity variances is 81;the sum of variances along the critical path is 64.What is the probability that the project will take 130 or more days to complete?
(Multiple Choice)
4.8/5
(43)
A project organization that becomes permanent is often referred to as a:
(Multiple Choice)
4.9/5
(40)
The expected activity time in PERT analysis is calculated as:
(Multiple Choice)
4.8/5
(27)
The network below represents a project being analyzed by the critical path method.Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=10,and J=6.
a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?

(Essay)
4.8/5
(34)
The ________ distribution is used by PERT analysis to calculate expected activity times and variances.
(Multiple Choice)
4.8/5
(41)
Which of the following statements regarding Gantt charts is true?
(Multiple Choice)
4.8/5
(35)
PERT calculations typically include the duration variance of each activity.What is the purpose of this calculation,i.e.what's the role of variances in PERT analysis?
(Essay)
4.9/5
(38)
Which of the following statements regarding critical paths is true?
(Multiple Choice)
4.9/5
(28)
Which of these statements regarding time-cost tradeoffs in CPM networks is true?
(Multiple Choice)
4.8/5
(34)
Given the project within the table below,calculate the following:
a.The critical path
b.The minimum project duration
c.The amount of slack for each activity


(Essay)
4.8/5
(36)
Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64.There is a .90 probability that the project will be completed before approximately day:
(Multiple Choice)
4.9/5
(35)
What are the three phases of a project? Describe each in a sentence or two.
(Essay)
4.9/5
(45)