Exam 3: Managing Projects
Exam 1: Operations and Productivity127 Questions
Exam 2: The Global Environment and Operations Strategy119 Questions
Exam 3: Managing Projects120 Questions
Exam 4: Forecasting Demand140 Questions
Exam 5: Product Design118 Questions
Exam 6: Quality Management and International Standards123 Questions
Exam 7: Process Design108 Questions
Exam 8: Location Decisions121 Questions
Exam 9: Layout Decisions146 Questions
Exam 10: Job Design and Work Measurement154 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Managing Inventory163 Questions
Exam 13: Aggregate Scheduling116 Questions
Exam 14: Material Requirements Planning Mrpand Erp113 Questions
Exam 15: Scheduling for the Short-Term116 Questions
Exam 16: Jit,lean Operations,and the Toyota Production System115 Questions
Exam 17: Maintenance and Reliability Decisions111 Questions
Exam 18: Sustainability80 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity Planning96 Questions
Exam 21: Supply Chain Modeling55 Questions
Exam 22: Decision Modeling97 Questions
Exam 23: Linear Programming Models88 Questions
Exam 24: Transportation Modeling89 Questions
Exam 25: Queuing Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Modeling with Simulation75 Questions
Select questions type
An activity on a PERT network has these time estimates: optimistic = 2,most likely = 5,and pessimistic = 10.What is its expected activity time?
(Multiple Choice)
4.8/5
(40)
A simple CPM network has five activities,A,B,C,D,and E.A is an immediate predecessor of C and of D.B is also an immediate predecessor of C and of D.C and D are both immediate predecessors of E.Which of the following statements is true?
(Multiple Choice)
4.9/5
(42)
A project manager is interested in crashing a project with variable activity times.Which of the following tools should he/she employ?
(Multiple Choice)
5.0/5
(31)
Ethical issues that may arise in projects large and small include:
(Multiple Choice)
4.7/5
(39)
PERT,but not CPM,has the ability to consider the precedence relationships in a project.
(True/False)
4.7/5
(30)
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for activity A?
b.What is the crash cost per unit time for activity B?
c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?

(Essay)
4.9/5
(23)
Which of the following is NOT performed by Microsoft Project?
(Multiple Choice)
4.8/5
(42)
An activity on a PERT network has these time estimates: optimistic = 2,most likely = 3,and pessimistic = 8.What is its expected activity time and variance?
(Multiple Choice)
4.8/5
(34)
If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1,500,what is the crash cost per period?
(Multiple Choice)
4.9/5
(31)
WBS stands for which of the following project management tools?
(Multiple Choice)
4.9/5
(34)
The project organization works best when which of the following conditions are satisfied? I.Work tasks can be defined with a specific goal and deadline.
II.The job is typical and familiar to the existing organization.
III.The work contains interrelated tasks requiring specialized skills.
IV.The project is temporary but unimportant to long-term organizational success.
V.The project cuts across organizational lines.
(Multiple Choice)
4.9/5
(35)
________ is decreasing activity time in a network to reduce time on the critical path so total completion time is reduced.
(Essay)
4.8/5
(32)
Showing 41 - 60 of 120
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)