Exam 3: Managing Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

An activity on a PERT network has these time estimates: optimistic = 2,most likely = 5,and pessimistic = 10.What is its expected activity time?

(Multiple Choice)
4.8/5
(40)

Identify several advantages of using PERT (and CPM).

(Essay)
4.9/5
(41)

The difference between AON and AOA networks is that:

(Multiple Choice)
4.9/5
(41)

A simple CPM network has five activities,A,B,C,D,and E.A is an immediate predecessor of C and of D.B is also an immediate predecessor of C and of D.C and D are both immediate predecessors of E.Which of the following statements is true?

(Multiple Choice)
4.9/5
(42)

A project manager is interested in crashing a project with variable activity times.Which of the following tools should he/she employ?

(Multiple Choice)
5.0/5
(31)

Which of the following projects were completed by Bechtel?

(Multiple Choice)
4.8/5
(40)

A code of ethics especially for project managers:

(Multiple Choice)
4.8/5
(38)

What is the basic difference between PERT and CPM?

(Essay)
5.0/5
(36)

Ethical issues that may arise in projects large and small include:

(Multiple Choice)
4.7/5
(39)

PERT,but not CPM,has the ability to consider the precedence relationships in a project.

(True/False)
4.7/5
(30)

A project organization:

(Multiple Choice)
4.9/5
(33)

Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below. Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.    a.What is the crash cost per unit time for activity A? b.What is the crash cost per unit time for activity B? c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost? d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost? e.Assuming no other paths become critical,how much can this project be shortened at what total added cost? a.What is the crash cost per unit time for activity A? b.What is the crash cost per unit time for activity B? c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost? d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost? e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?

(Essay)
4.9/5
(23)

Which of the following is NOT performed by Microsoft Project?

(Multiple Choice)
4.8/5
(42)

The phases of project management are:

(Multiple Choice)
4.9/5
(36)

An activity on a PERT network has these time estimates: optimistic = 2,most likely = 3,and pessimistic = 8.What is its expected activity time and variance?

(Multiple Choice)
4.8/5
(34)

If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1,500,what is the crash cost per period?

(Multiple Choice)
4.9/5
(31)

WBS stands for which of the following project management tools?

(Multiple Choice)
4.9/5
(34)

The project organization works best when which of the following conditions are satisfied? I.Work tasks can be defined with a specific goal and deadline. II.The job is typical and familiar to the existing organization. III.The work contains interrelated tasks requiring specialized skills. IV.The project is temporary but unimportant to long-term organizational success. V.The project cuts across organizational lines.

(Multiple Choice)
4.9/5
(35)

________ is decreasing activity time in a network to reduce time on the critical path so total completion time is reduced.

(Essay)
4.8/5
(32)

Which of the following statements about Bechtel is true?

(Multiple Choice)
4.8/5
(24)
Showing 41 - 60 of 120
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)