Activity R on a CPM network has predecessors M and N,and has successor S.R has duration 5.N's late finish is 18,while M's is 20.S's late start is 14.Which of the following is definitely true?

(Multiple Choice)
4.9/5
(24)

Project managers have their own code of ethics,established by the Project Management Institute.

(True/False)
4.9/5
(31)

Describe in words how to calculate a project's standard deviation.What assumption allows that calculation to be accurate?

(Essay)
4.9/5
(32)

One responsibility of a project manager is to make sure that the project meets its quality goals.

(True/False)
4.9/5
(40)

Which of the following statements regarding PERT times is true?

(Multiple Choice)
4.8/5
(38)

A network has been crashed to the point where all activities are critical.Additional crashing:

(Multiple Choice)
4.9/5
(39)

The fundamental difference between PERT and CPM is that PERT uses the beta distribution for crashing projects while CPM uses cost estimates.

(True/False)
4.8/5
(24)

What are some of the ethical issues faced by project managers?

(Essay)
4.9/5
(31)

The beta distribution is used in project management to:

(Multiple Choice)
4.9/5
(34)

A simple CPM network has three activities,D,E,and F.D is an immediate predecessor of E and of F.E is an immediate predecessor of F.The activity durations are D=4,E=3,F=8.

(Multiple Choice)
4.9/5
(33)

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.

(Multiple Choice)
4.7/5
(27)

What is the objective of critical path analysis?

(Essay)
4.9/5
(31)

A network consists of the following list.Times are given in weeks. A network consists of the following list.Times are given in weeks.    a.Draw the network diagram. b.Which activities form the critical path? c.How much slack exists at activities A and F? d.What is the duration of the critical path? a.Draw the network diagram. b.Which activities form the critical path? c.How much slack exists at activities A and F? d.What is the duration of the critical path?

(Essay)
4.9/5
(41)

Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below. Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.    a.What is the crash cost per unit time for each of the three activities? b.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost? c.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost? a.What is the crash cost per unit time for each of the three activities? b.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost? c.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?

(Essay)
4.9/5
(34)

Which of the following statements regarding PERT times is true?

(Multiple Choice)
4.9/5
(22)

The standard deviation of project duration is the average of the standard deviation of all activities on the critical path.

(True/False)
4.9/5
(40)

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.

(Multiple Choice)
4.8/5
(45)

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?

(Multiple Choice)
4.8/5
(38)

Which of the following statements regarding CPM networks is true?

(Multiple Choice)
4.8/5
(45)

The shortest of all paths through the network is the critical path.

(True/False)
4.8/5
(36)