Exam 3: Managing Projects
Exam 1: Operations and Productivity127 Questions
Exam 2: The Global Environment and Operations Strategy119 Questions
Exam 3: Managing Projects120 Questions
Exam 4: Forecasting Demand140 Questions
Exam 5: Product Design118 Questions
Exam 6: Quality Management and International Standards123 Questions
Exam 7: Process Design108 Questions
Exam 8: Location Decisions121 Questions
Exam 9: Layout Decisions146 Questions
Exam 10: Job Design and Work Measurement154 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Managing Inventory163 Questions
Exam 13: Aggregate Scheduling116 Questions
Exam 14: Material Requirements Planning Mrpand Erp113 Questions
Exam 15: Scheduling for the Short-Term116 Questions
Exam 16: Jit,lean Operations,and the Toyota Production System115 Questions
Exam 17: Maintenance and Reliability Decisions111 Questions
Exam 18: Sustainability80 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity Planning96 Questions
Exam 21: Supply Chain Modeling55 Questions
Exam 22: Decision Modeling97 Questions
Exam 23: Linear Programming Models88 Questions
Exam 24: Transportation Modeling89 Questions
Exam 25: Queuing Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Modeling with Simulation75 Questions
Select questions type
Activity R on a CPM network has predecessors M and N,and has successor S.R has duration 5.N's late finish is 18,while M's is 20.S's late start is 14.Which of the following is definitely true?
(Multiple Choice)
4.9/5
(24)
Project managers have their own code of ethics,established by the Project Management Institute.
(True/False)
4.9/5
(31)
Describe in words how to calculate a project's standard deviation.What assumption allows that calculation to be accurate?
(Essay)
4.9/5
(32)
One responsibility of a project manager is to make sure that the project meets its quality goals.
(True/False)
4.9/5
(40)
Which of the following statements regarding PERT times is true?
(Multiple Choice)
4.8/5
(38)
A network has been crashed to the point where all activities are critical.Additional crashing:
(Multiple Choice)
4.9/5
(39)
The fundamental difference between PERT and CPM is that PERT uses the beta distribution for crashing projects while CPM uses cost estimates.
(True/False)
4.8/5
(24)
A simple CPM network has three activities,D,E,and F.D is an immediate predecessor of E and of F.E is an immediate predecessor of F.The activity durations are D=4,E=3,F=8.
(Multiple Choice)
4.9/5
(33)
Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. 

(Multiple Choice)
4.7/5
(27)
A network consists of the following list.Times are given in weeks.
a.Draw the network diagram.
b.Which activities form the critical path?
c.How much slack exists at activities A and F?
d.What is the duration of the critical path?

(Essay)
4.9/5
(41)
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for each of the three activities?
b.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
c.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?

(Essay)
4.9/5
(34)
Which of the following statements regarding PERT times is true?
(Multiple Choice)
4.9/5
(22)
The standard deviation of project duration is the average of the standard deviation of all activities on the critical path.
(True/False)
4.9/5
(40)
Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. 

(Multiple Choice)
4.8/5
(45)
A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?
(Multiple Choice)
4.8/5
(38)
Which of the following statements regarding CPM networks is true?
(Multiple Choice)
4.8/5
(45)
The shortest of all paths through the network is the critical path.
(True/False)
4.8/5
(36)