Exam 14: Material Requirements Planning Mrp and Erp

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A bill of material lists all components, ingredients, and materials needed to produce one unit of an end item.

(True/False)
4.8/5
(30)

__________ is a system that allows, with MRP in place, inventory data to be augmented by other resource variables.

(Essay)
4.9/5
(40)

Consider the bill of material for Product J and the data given in the following table. The gross requirements for J are 200 units in week 6 and 250 units in week 8. Develop the MRP tables for each item for an 8-week planning period. Use the lot-for-lot lot-sizing rule. Consider the bill of material for Product J and the data given in the following table. The gross requirements for J are 200 units in week 6 and 250 units in week 8. Develop the MRP tables for each item for an 8-week planning period. Use the lot-for-lot lot-sizing rule.    Consider the bill of material for Product J and the data given in the following table. The gross requirements for J are 200 units in week 6 and 250 units in week 8. Develop the MRP tables for each item for an 8-week planning period. Use the lot-for-lot lot-sizing rule.

(Essay)
4.9/5
(30)

Which of the following statements regarding MRP in services is true?

(Multiple Choice)
4.9/5
(44)

__________ is a lot-sizing technique that generates exactly what is required to meet the plan.

(Short Answer)
4.8/5
(29)

__________ are a way of allowing a segment of the master schedule to be designated as "not to be rescheduled."

(Short Answer)
4.9/5
(30)

MRP is an excellent tool for scheduling products with variable lead times.

(True/False)
4.8/5
(33)

The extension of MRP which extends to resources such as labor hours and machine hours, as well as to order entry, purchasing, and direct interface with customers and suppliers is

(Multiple Choice)
4.8/5
(36)

An error has been detected in the technical drawing of a product about to be placed on a master production schedule. The part should be 9" by 12", not 9 cm by 12 cm; further, the part should be stainless steel, not ordinary steel. What document transmits the needed change? Where is the corrected information recorded? Why is this important to the master production schedule?

(Essay)
4.8/5
(32)

Closed-loop MRP systems allow production planners to move work between time periods to smooth the load or to at least bring it within capacity.

(True/False)
4.7/5
(40)

In continuous (stock-to-forecast) operations, the master production schedule is usually expressed in terms of

(Multiple Choice)
4.9/5
(35)

Effective use of MRP and other dependent demand models does not require which of the following?

(Multiple Choice)
4.8/5
(33)

The time-phased product structure, unlike the bill of material, adds the concept of lead times.

(True/False)
4.9/5
(31)

Each R requires 4 of component S; each S requires 3 of part T. The lead time for assembly of R is 1 week. The lead time for the manufacture of S is 2 weeks. The lead time for the procurement of T is 6 weeks. The cumulative lead time for R is __________ weeks.

(Multiple Choice)
4.8/5
(43)

How does the process choice of an organization affect the basis of its master production schedule?

(Essay)
4.8/5
(36)

A(n) __________ system is packaged business software that automates and integrates the majority of their business processes, shares common data and practices across the entire enterprise, and produces and accesses information in a real-time environment.

(Short Answer)
4.8/5
(25)

Finite capacity scheduling, unlike MRP, recognizes the capacity limitations of departments and machines when building schedules.

(True/False)
4.9/5
(35)

Which of the following statements regarding lot-sizing is true?

(Multiple Choice)
4.8/5
(30)

A(n) __________ can illustrate whether a work center has been scheduled beyond its capacity.

(Essay)
4.8/5
(33)

Enterprise resource planning (ERP)

(Multiple Choice)
4.8/5
(32)
Showing 121 - 140 of 172
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)