Exam 17: Supplement J Operations Scheduling
Exam 1: Using Operations to Create Value115 Questions
Exam 2: Process Strategy and Analysis239 Questions
Exam 3: Quality and Performance198 Questions
Exam 4: Capacity Planning120 Questions
Exam 5: Constraint Management136 Questions
Exam 6: Lean Systems166 Questions
Exam 7: Project Management139 Questions
Exam 8: Forecasting150 Questions
Exam 9: Inventory Management205 Questions
Exam 10: Operations Planning and Scheduling149 Questions
Exam 11: Resource Planning124 Questions
Exam 12: Supply Chain Design77 Questions
Exam 13: Supply Chain Logistic Networks114 Questions
Exam 14: Supply Chain Integration120 Questions
Exam 15: Supply Chain Sustainability78 Questions
Exam 16: Supplement A Decision Making107 Questions
Exam 17: Supplement J Operations Scheduling123 Questions
Exam 18: Supplement K Layout39 Questions
Exam 19: Supplement B Waiting Lines111 Questions
Exam 20: Supplement C Special Inventory Models53 Questions
Exam 21: Supplement D Linear Programming87 Questions
Exam 22: Supplement E Simulation54 Questions
Exam 23: Supplement F Financial Analysis55 Questions
Exam 24: Supplement G Acceptance Sampling Plans87 Questions
Exam 25: Supplement H Measuring Output Rates108 Questions
Exam 26: Supplement I Learning Curve Analysis50 Questions
Select questions type
In the context of operations scheduling, total inventory is equal to:
(Multiple Choice)
4.9/5
(40)
Table J.12 The Feast
Janice prepares a medley of pastas for her brother Tony. Each of the pastas must first be rolled and then formed (or in some cases stuffed) before cooking. The required time on each machine in minutes is indicated in the table.
-Janice uses Johnson's rule to schedule her pasta production. What is the average flow time of her seven pastas?

(Multiple Choice)
4.8/5
(41)
Table J.2
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.
-Stu schedules his assignments using the critical ratio criterion. How many assignments are late?

(Multiple Choice)
4.8/5
(35)
Table J.2
Stu Dent reviews the syllabi he received on the first day of class and pulls out his planner. He has seven major assignments that must be completed before the end of the semester.
-Develop an SPT sequence and calculate the average number of assignments Stu has this semester.

(Multiple Choice)
4.8/5
(36)
An appropriate objective for a manufacturing firm is to maximize total inventory.
(True/False)
4.8/5
(29)
A rule that establishes a job's priority based on one piece of information, such as how long it will take to process or when the job arrived, is a(n) ________.
(Essay)
4.9/5
(41)
The percent of work time productively spent by an employee or a machine is called:
(Multiple Choice)
4.8/5
(41)
The earliest due date (EDD) rule gives the job with the shortest processing time the highest priority.
(True/False)
4.9/5
(34)
Table J.8
Auto Data produces custom engineering testing equipment. The following six jobs are currently in the design department. The time since each one arrived, the processing time, and the due date are shown below. All times are expressed in terms of days. Let now be the beginning of Day 1.
-Using the information in Table J.8 and the FCFS rule, what is the average days past due?

(Multiple Choice)
4.8/5
(34)
Table J.18
-Use the information in Table J.18 and sequence the jobs using the EDD rule. What is the average flow time?

(Multiple Choice)
4.7/5
(36)
Table J.6
All of the following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.
-Use the information in Table J.6. What is the job sequence at Workstation A, using the critical ratio rule?

(Multiple Choice)
5.0/5
(27)
Table J.17
A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.
-Using the information in Table J.17 and Johnson's rule, develop a schedule that minimizes makespan for these seven jobs. Assume that job C could be neatly split into two equal parts, each having half of the processing time on each machine as the full job C. Using your original sequence, but splitting job C, what is the makespan for the seven jobs?

(Multiple Choice)
4.8/5
(38)
A first-come, first-served schedule minimizes the average flow time for all jobs.
(True/False)
4.9/5
(45)
Table J.11
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.
-Using the information in Table J.11 and the critical ratio rule, what should be the sequence of jobs processed at Q45?

(Multiple Choice)
4.8/5
(31)
Table J.8
Auto Data produces custom engineering testing equipment. The following six jobs are currently in the design department. The time since each one arrived, the processing time, and the due date are shown below. All times are expressed in terms of days. Let now be the beginning of Day 1.
-Using the information in Table J.8 and the SPT rule, what is the average days past due?

(Multiple Choice)
4.8/5
(37)
When using the critical ratio (CR) priority sequencing rule:
(Multiple Choice)
4.8/5
(45)
Consider this list of jobs that have just arrived and are ready for processing. They all require processing first on machine 1 and then on machine 2. Both machines are now idle. Develop a schedule that minimizes makespan and calculate this makespan time. Now assume that each job can be split into two jobs, each having half the duration on both machine 1 and machine 2. Using the original sequence that minimized average flow time, calculate the flow times for all split jobs What is the effect of this new schedule on the average flow time for these split jobs?


(Essay)
4.8/5
(44)
Showing 81 - 100 of 123
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)