Exam 13: Progress and Performance Measurement and Evaluation

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A project manager receives the following information on his project: PV = 4,500, AC =4,000, EV = 5,000. How well is the project doing in terms of budget?

(Multiple Choice)
4.9/5
(33)

What is a "rubber baseline" and how does it undermine project control?

(Essay)
4.8/5
(36)

Baseline project budgets are derived from

(Multiple Choice)
4.9/5
(32)

The baseline is derived from merging information from the work packages with the project network.

(True/False)
4.8/5
(32)

A project manager notices that $5,560 worth of work that was scheduled to be completed at this time has not been accomplished. She knows this by looking at the

(Multiple Choice)
4.8/5
(35)

The schedule variance is the best way to get an accurate assessment of schedule performance.

(True/False)
4.9/5
(48)

In monitoring project time (schedule) performance, actual performance should be compared to

(Multiple Choice)
4.8/5
(34)

Schedule variance measures progress in time units.

(True/False)
4.8/5
(41)

Conducting an earned value analysis requires three data elements. Identify the acronyms for each and describe what they are.

(Short Answer)
4.8/5
(32)

The third step in the project control process for measuring and evaluating project performance is to

(Multiple Choice)
4.8/5
(31)

Although it is very difficult to measure, measuring technical performance is as important as measuring schedule and cost performance.

(True/False)
4.9/5
(37)

A negative CV indicates the project is currently ________ budget.

(Multiple Choice)
4.8/5
(34)

The earned value system starts with the time-phased costs that provide the project baseline, which is called the

(Multiple Choice)
4.7/5
(40)

Which of the following are required to assess the current status of a project using the earned-value cost / schedule system?

(Multiple Choice)
4.9/5
(30)

The chief financial officer receives the following information on a project: PV = 10,000, EV = 12,000, AC = 8,000, BAC = 20,000, EAC = 13,333. How is the project doing in terms of schedule?

(Multiple Choice)
4.7/5
(32)

Two major reasons for creating a baseline are to monitor and report progress and to estimate cash flow.

(True/False)
4.8/5
(38)

If the cost of labor and materials has not been separated there is additional analysis required to determine the cause of the calculated variance.

(True/False)
4.7/5
(29)

Conditions or scope can change during execution, which, in turn, will require a change to the __________ plan to recognize the new information.

(Multiple Choice)
4.9/5
(38)

When revising the estimated cost at completion, there are two approaches. The EACre is determined by experts in the field and the EACf is a mathematical approach which assumes the CPI as the basis for forecasting cost at completion.

(True/False)
5.0/5
(40)

The project network schedule is derived from the _______ and it serves as the baseline to compare against actual performance.

(Multiple Choice)
4.8/5
(39)
Showing 21 - 40 of 98