Exam 13: Progress and Performance Measurement and Evaluation
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection101 Questions
Exam 3: Organization: Structure and Culture102 Questions
Exam 4: Defining the Project112 Questions
Exam 5: Estimating Project Times and Costs95 Questions
Exam 6: Developing a Project Schedule128 Questions
Exam 7: Managing Risk105 Questions
Exam 8: Scheduling Resources and Costs114 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager98 Questions
Exam 11: Managing Project Teams103 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations102 Questions
Exam 13: Progress and Performance Measurement and Evaluation98 Questions
Exam 14: Project Closure97 Questions
Exam 15: Agile Project Management94 Questions
Exam 16: International Projects103 Questions
Select questions type
The ________ variance is the difference between the earned value and the actual costs for the work completed to date.
(Multiple Choice)
5.0/5
(34)
Progress and performance can be measured quantitatively as well as qualitatively.
(True/False)
4.8/5
(33)
A negative cost variance combined with a negative schedule variance is an indicator of
(Multiple Choice)
4.8/5
(37)
A program financial accountant learns that a project is currently earning $1.15 for each dollar actually spent. The accountant is able to determine this by looking at the
(Multiple Choice)
4.9/5
(41)
Which of the following is not one of the four steps for measuring and evaluating project performance?
(Multiple Choice)
4.7/5
(34)
Which of the following is not a benefit of Earned Value Management?
(Multiple Choice)
5.0/5
(28)
The PCIC index measures the project percent complete in relation to the actual resources used so far on the project.
(True/False)
4.9/5
(24)
The _________ index measures the project percent complete in relation to the resources that were budgeted.
(Multiple Choice)
4.9/5
(27)
Identify and describe two methods for tracking and trending schedule performance.
(Essay)
4.8/5
(32)
For a more complex project, statistical analysis can be applied to a control chart to identify potential causes of schedule deviation.
(True/False)
4.7/5
(32)
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the
(Multiple Choice)
4.9/5
(29)
A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion,
(Multiple Choice)
4.8/5
(34)
Given an EAC of $10,000 and a BAC of $15,000, the project is expected to be completed _________.
(Multiple Choice)
4.9/5
(28)
The ratio that measures the amount of value each remaining dollar in the budget must earn to stay within the budget is the _________.
(Multiple Choice)
5.0/5
(32)
The indicator that tells you the planned time-phased value of the work that is scheduled is the _______________.
(Multiple Choice)
4.9/5
(30)
Showing 61 - 80 of 98
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)