Exam 13: Progress and Performance Measurement and Evaluation

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The ________ variance is the difference between the earned value and the actual costs for the work completed to date.

(Multiple Choice)
5.0/5
(34)

A Control Chart can be used to estimate schedule trends.

(True/False)
4.8/5
(33)

Progress and performance can be measured quantitatively as well as qualitatively.

(True/False)
4.8/5
(33)

A negative cost variance combined with a negative schedule variance is an indicator of

(Multiple Choice)
4.8/5
(37)

A project manager would be glad to see a TCPI of 1.2.

(True/False)
4.8/5
(30)

A program financial accountant learns that a project is currently earning $1.15 for each dollar actually spent. The accountant is able to determine this by looking at the

(Multiple Choice)
4.9/5
(41)

Which of the following is not one of the four steps for measuring and evaluating project performance?

(Multiple Choice)
4.7/5
(34)

Which of the following is not a benefit of Earned Value Management?

(Multiple Choice)
5.0/5
(28)

The PCIC index measures the project percent complete in relation to the actual resources used so far on the project.

(True/False)
4.9/5
(24)

The _________ index measures the project percent complete in relation to the resources that were budgeted.

(Multiple Choice)
4.9/5
(27)

Identify and describe two methods for tracking and trending schedule performance.

(Essay)
4.8/5
(32)

For a more complex project, statistical analysis can be applied to a control chart to identify potential causes of schedule deviation.

(True/False)
4.7/5
(32)

When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the

(Multiple Choice)
4.9/5
(29)

A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion,

(Multiple Choice)
4.8/5
(34)

The cost variance for a project is calculated by

(Multiple Choice)
4.9/5
(35)

Given an EAC of $10,000 and a BAC of $15,000, the project is expected to be completed _________.

(Multiple Choice)
4.9/5
(28)

What is scope creep and how does it impact project control?

(Essay)
4.9/5
(28)

The ratio that measures the amount of value each remaining dollar in the budget must earn to stay within the budget is the _________.

(Multiple Choice)
5.0/5
(32)

Causes for scope creep can include

(Multiple Choice)
4.7/5
(28)

The indicator that tells you the planned time-phased value of the work that is scheduled is the _______________.

(Multiple Choice)
4.9/5
(30)
Showing 61 - 80 of 98
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)