Exam 11: CompTIA Project+
Exam 1: CompTIA A+ Certification Exam: Core 1471 Questions
Exam 2: CompTIA A+ Certification Exam: Core 2409 Questions
Exam 3: CompTIA Advanced Security Practitioner (CASP+) CAS-003442 Questions
Exam 4: CompTIA Advanced Security Practitioner (CASP+) CAS-004107 Questions
Exam 5: CompTIA Cloud Essentials+165 Questions
Exam 6: CompTIA CySA+ Certification Exam (CS0-002)294 Questions
Exam 7: CompTIA Cloud+ (CV0-002)48 Questions
Exam 8: CompTIA Cloud+67 Questions
Exam 9: CompTIA IT Fundamentals387 Questions
Exam 10: CompTIA Network+829 Questions
Exam 11: CompTIA Project+540 Questions
Exam 12: CompTIA PenTest+ Certification Exam165 Questions
Exam 13: CompTIA Server+66 Questions
Exam 14: CompTIA Server+ Certification Exam779 Questions
Exam 15: CompTIA Security+1 k+ Questions
Exam 16: CompTIA Security+ 2021129 Questions
Exam 17: CompTIA CTT+ Essentials378 Questions
Exam 18: CompTIA Linux+252 Questions
Select questions type
A project manager is creating the monthly report for top management. The project manager has collected the information below: AC = 100 PV = 80 EV = 120 Based on this information, the CPI reflects which of the following about the project?
(Multiple Choice)
4.7/5
(25)
A company has been trying to implement a product with multiple challenges for more than two years. Both the company and the vendor mutually agree to cancel the project. Which of the following should be issued?
(Multiple Choice)
4.8/5
(37)
A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered. Which of the following are NOST likely missing from the project? (Select two.)
(Multiple Choice)
4.8/5
(35)
A meeting has taken place with quality assurance tram members and the project manager. Which of the following events would MOST likely have triggered the meeting?
(Multiple Choice)
4.9/5
(33)
During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.
Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

(Multiple Choice)
4.9/5
(30)
A project manager detects low performance from a team member who previously demonstrated to be a highly skilled asset. The team member explains that being part of two teams is too time consuming. This is a disadvantage of having:
(Multiple Choice)
4.9/5
(41)
A change is being implemented on a project, and while in testing, it becomes clear that the change cannot be finalized due to the severe impact it would have on other critical systems. Which of the following should the team consult to determine which actions to take?
(Multiple Choice)
4.8/5
(41)
A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?
(Multiple Choice)
4.8/5
(44)
Which of the following are characteristics of a matrix organization? (Choose three.)
(Multiple Choice)
4.8/5
(34)
A WBS is being developed for a project. Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
(Multiple Choice)
4.9/5
(33)
A post implementation review is being performed as a part of project closure. Which of the following are applicable areas that the review should cover? (Choose two.)
(Multiple Choice)
4.9/5
(41)
Which of the following elements should be included on a responsibility assignment matrix?
(Multiple Choice)
4.9/5
(31)
A project manager is informed that the project sponsor was terminated from the project effective immediately. To ensure business continuity, the project manager has been asked to assume additional tasks to complete the project on time. Many of these tasks were performed by the former project sponsor. Which of the following types of change does this illustrate?
(Multiple Choice)
4.9/5
(41)
A team member has completed an assigned task. Which of the following roles should be notified FIRST?
(Multiple Choice)
4.8/5
(51)
Which of the following documents should be used FIRST when addressing a vendor that is not complying with the project deliverables?
(Multiple Choice)
4.9/5
(46)
Several team members report that meeting objectives are not being met. Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)
(Multiple Choice)
4.8/5
(40)
At a weekly project team meeting, it is apparent the project is over budget. The project manager needs to determine the reason for this issue. Which of the following documents should MOST likely be analyzed to obtain the answer?
(Multiple Choice)
4.9/5
(39)
When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?
(Multiple Choice)
4.7/5
(39)
During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor's tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months. Which of the following should have occurred to prevent this issue?
(Multiple Choice)
4.7/5
(46)
Showing 261 - 280 of 540
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)