Exam 11: CompTIA Project+
Exam 1: CompTIA A+ Certification Exam: Core 1471 Questions
Exam 2: CompTIA A+ Certification Exam: Core 2409 Questions
Exam 3: CompTIA Advanced Security Practitioner (CASP+) CAS-003442 Questions
Exam 4: CompTIA Advanced Security Practitioner (CASP+) CAS-004107 Questions
Exam 5: CompTIA Cloud Essentials+165 Questions
Exam 6: CompTIA CySA+ Certification Exam (CS0-002)294 Questions
Exam 7: CompTIA Cloud+ (CV0-002)48 Questions
Exam 8: CompTIA Cloud+67 Questions
Exam 9: CompTIA IT Fundamentals387 Questions
Exam 10: CompTIA Network+829 Questions
Exam 11: CompTIA Project+540 Questions
Exam 12: CompTIA PenTest+ Certification Exam165 Questions
Exam 13: CompTIA Server+66 Questions
Exam 14: CompTIA Server+ Certification Exam779 Questions
Exam 15: CompTIA Security+1 k+ Questions
Exam 16: CompTIA Security+ 2021129 Questions
Exam 17: CompTIA CTT+ Essentials378 Questions
Exam 18: CompTIA Linux+252 Questions
Select questions type
A project manager wishes to track a project's performance against the original approved schedule. Which of the following steps is necessary to capture the needed information?
(Multiple Choice)
4.8/5
(28)
A project manager must create documentation before the project kickoff meeting. Which of the following documents will identify the project, introduce the project manager, and establish authority in the project?
(Multiple Choice)
4.8/5
(36)
Which of the following job roles is primarily tasked with communicating the project timeline changes?
(Multiple Choice)
4.7/5
(39)
Which of the following describes how a project is related to a program?
(Multiple Choice)
4.9/5
(35)
Which of the following are MOST likely the responsibilities of the PMO? (Choose two.)
(Multiple Choice)
4.9/5
(41)
A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks. Which of the following represents the number of days the project schedule will be delayed?
(Multiple Choice)
5.0/5
(44)
During the planning phase of a construction project, the project team discovers the site is the nesting area birds, and construction could disrupt the bird's patterns. Lobbyists would like the team to move the project down the road. Which of the following constraint and influencer types are involved in this scenario?
(Multiple Choice)
4.8/5
(46)
The chairperson of the board is visiting from another country and wishes to meet the project team members. The next project team meeting will be held next week, but the chairperson is leaving before the meeting. Which of the following actions should the project manager take?
(Multiple Choice)
4.8/5
(33)
A vendor has accepted a proposed project from a customer. Which of the following is MOST likely to be the first document created by the project manager?
(Multiple Choice)
4.8/5
(37)
A project manager is determining a project's critical path to report the projected completion date to stakeholders. Which of the following information will be required? (Select two.)
(Multiple Choice)
4.7/5
(42)
Which of the following documents ensures two parties do not share contractually binding information?
(Multiple Choice)
4.7/5
(38)
A company hires an outside vendor to provide 24/7 support. Which of the following documents would determine the contractual obligations?
(Multiple Choice)
5.0/5
(35)
An active project has a CPI of 0.92. Which of the following can be determined?
(Multiple Choice)
4.8/5
(27)
A project manager was reprimanded for failing to complete timely status reports and providing mixed messaging about a project's performance. Which of the following would be responsible for discussing and resolving this issue?
(Multiple Choice)
4.8/5
(42)
A project has a ??? of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do NEXT?
(Multiple Choice)
4.9/5
(33)
Which of the following documents does a vendor rely on to commit funding and resources to a project?
(Multiple Choice)
4.9/5
(35)
A team member has completed a project task. Which of the following is the FASTEST method to communicate the task completion?
(Multiple Choice)
4.9/5
(35)
Which of the following primary factors are used to prioritize the development of risk response strategies? (Choose two.)
(Multiple Choice)
4.9/5
(35)
A company just announced all third-party vendors must provide ten cybersecurity resources within six weeks. Which of the following documents should the project manager create LAST?
(Multiple Choice)
4.9/5
(52)
Which of the following make up a company's portfolio? (Choose two.)
(Multiple Choice)
4.8/5
(35)
Showing 481 - 500 of 540
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)