A project manager is scheduling activities and determines one activity cannot be completed until another activity is completed. Which of the following dependency relationships is represented?

(Multiple Choice)
4.9/5
(39)

A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule. Which of the following is the FIRST step the project manager should take?

(Multiple Choice)
4.8/5
(42)

A customer has requested a new feature be included in the next iterative release. The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which of the following is the MOST appropriate scheduling action?

(Multiple Choice)
4.7/5
(31)

The project manager for a TV tower construction project receives notification that a strong storm is expected the following week. Which of the following should the project manager do NEXT?

(Multiple Choice)
4.9/5
(37)

A project sponsor approaches the project manager with a change request. During the conversation, the project sponsor claims to understand the impact of the change to the project length and has the budget to handle the cost. The sponsor also tells the project manager to send whatever needs a signature. The project manager's NEXT step should be to:

(Multiple Choice)
4.9/5
(41)

A project manager needs status on the project timeline. Which of the following team members should provide an update?

(Multiple Choice)
4.9/5
(38)

Which of the following is a schedule that illustrates the duration of an activity?

(Multiple Choice)
4.9/5
(39)

Communication on a project is flowing well. Team members are motivated, and they are allowed to make decisions about their work. Which of the following management styles is the project manager MOST likely using?

(Multiple Choice)
4.9/5
(42)

A Chief Executive Officer (CEO) has approached a project team member to request a project change. Which of the following would be the BEST step for the project manager to take to prevent scope creep?

(Multiple Choice)
4.9/5
(39)

A customer is in the early planning stages of a technology rebuild. To gain a better understanding of the possible solutions, which of the following documents should the customer send to prospective vendors?

(Multiple Choice)
4.7/5
(35)

A project manager is working on the project charter. Which of the following phases does this describe?

(Multiple Choice)
4.9/5
(37)

A key stakeholder cannot identify within the resource management plan where the project manager has authority to assign resources. Which of the following should the project manager use to answer the question?

(Multiple Choice)
4.8/5
(38)

The PMO is responsible for: (Choose two.)

(Multiple Choice)
4.9/5
(38)

A project team is showing off a new product prototype at a trade show, and potential customers are requesting more information. Which of the following is the MOST efficient way to provide more information?

(Multiple Choice)
4.9/5
(33)

A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?

(Multiple Choice)
4.7/5
(44)

A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented: Project description Draft project timeline and schedule Rough milestones Draft project budget Draft resources required High-level risk review Which of the following sections should be included in this document?

(Multiple Choice)
4.8/5
(36)

Language barriers will MOST likely influence a PM to:

(Multiple Choice)
5.0/5
(31)

An American publisher is participating in a workshop in Hong Kong with the purpose of updating a new book that will be launched in Japan next year. During the workshop, a deep and intense discussion occurs with other local publishers regarding the references the book may contain. Which of the following BEST describes the situation?

(Multiple Choice)
4.8/5
(33)

An agreement document that is intended to prevent two or more organizations from sharing specific, confidential information with anyone but each other is called:

(Multiple Choice)
4.9/5
(39)

A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?

(Multiple Choice)
4.8/5
(33)