Exam 11: CompTIA Project+
Exam 1: CompTIA A+ Certification Exam: Core 1471 Questions
Exam 2: CompTIA A+ Certification Exam: Core 2409 Questions
Exam 3: CompTIA Advanced Security Practitioner (CASP+) CAS-003442 Questions
Exam 4: CompTIA Advanced Security Practitioner (CASP+) CAS-004107 Questions
Exam 5: CompTIA Cloud Essentials+165 Questions
Exam 6: CompTIA CySA+ Certification Exam (CS0-002)294 Questions
Exam 7: CompTIA Cloud+ (CV0-002)48 Questions
Exam 8: CompTIA Cloud+67 Questions
Exam 9: CompTIA IT Fundamentals387 Questions
Exam 10: CompTIA Network+829 Questions
Exam 11: CompTIA Project+540 Questions
Exam 12: CompTIA PenTest+ Certification Exam165 Questions
Exam 13: CompTIA Server+66 Questions
Exam 14: CompTIA Server+ Certification Exam779 Questions
Exam 15: CompTIA Security+1 k+ Questions
Exam 16: CompTIA Security+ 2021129 Questions
Exam 17: CompTIA CTT+ Essentials378 Questions
Exam 18: CompTIA Linux+252 Questions
Select questions type
Tasks B and D start after Task A is completed. Task C starts after Tasks B and D are completed. task E starts after Task D is completed. Task H starts after task B is completed. Task G starts after Tasks C and H are completed. Task F starts after Task E is completed. Following are the durations of all tasks:
Which of the following tasks are on the critical path?

(Multiple Choice)
4.7/5
(46)
Which of the following risk strategies is represented by the purchase of insurance?
(Multiple Choice)
4.8/5
(36)
? new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
(Multiple Choice)
4.9/5
(36)
Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task C. If Task A starts on December 15, which of the following is the anticipated start date for Task D?
(Multiple Choice)
4.9/5
(34)
Which of the following will identify the MOST potential project risks?
(Multiple Choice)
4.8/5
(32)
A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?
(Multiple Choice)
4.8/5
(28)
A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days. Which of the following characteristics classifies this as a project?
(Multiple Choice)
4.8/5
(37)
The supervisor asks an engineer to be a project manager within the department. Of which of the following types of organizational structures is this an example?
(Multiple Choice)
4.9/5
(42)
A project team is in the process of risk planning. One of the team members identifies a weather-related risk, which may cause delivery delays. Which of the following is the BEST risk response strategy?
(Multiple Choice)
4.8/5
(31)
A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling. Which of the following resources has the authority to authorize this change?
(Multiple Choice)
4.9/5
(37)
A project scheduler has calculated the project's critical path. Which of the following activities would most likely occur NEXT?
(Multiple Choice)
4.8/5
(34)
Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process. Which of the following conflict resolution techniques has the project manager utilized?
(Multiple Choice)
4.8/5
(46)
Which of the following is the BEST reason to conduct regular risk reviews?
(Multiple Choice)
4.9/5
(40)
In which of the following circumstances would faxing be the MOST appropriate communication method?
(Multiple Choice)
4.9/5
(35)
A project sponsor wants to demonstrate progress on a deliverable to all stakeholders at the next tollgate meeting. This feature was not scheduled for this tollgate, but the project manager plans to add it to the next phase. Which of the following describes what the project manager is doing?
(Multiple Choice)
4.9/5
(28)
A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project. Which of the following are critical for the project manager to provide?
(Multiple Choice)
4.7/5
(40)
A contract review meeting has been scheduled with a non-performing vendor. The project manager has been asked to provide recommendations for continuous service improvements and removal of the vendor. Which of the following documents should the project manager review BEFORE the meeting?
(Multiple Choice)
4.7/5
(33)
A project team is composed of numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility. Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?
(Multiple Choice)
4.7/5
(38)
A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?
(Multiple Choice)
4.8/5
(31)
Showing 61 - 80 of 540