Exam 11: CompTIA Project+
Exam 1: CompTIA A+ Certification Exam: Core 1471 Questions
Exam 2: CompTIA A+ Certification Exam: Core 2409 Questions
Exam 3: CompTIA Advanced Security Practitioner (CASP+) CAS-003442 Questions
Exam 4: CompTIA Advanced Security Practitioner (CASP+) CAS-004107 Questions
Exam 5: CompTIA Cloud Essentials+165 Questions
Exam 6: CompTIA CySA+ Certification Exam (CS0-002)294 Questions
Exam 7: CompTIA Cloud+ (CV0-002)48 Questions
Exam 8: CompTIA Cloud+67 Questions
Exam 9: CompTIA IT Fundamentals387 Questions
Exam 10: CompTIA Network+829 Questions
Exam 11: CompTIA Project+540 Questions
Exam 12: CompTIA PenTest+ Certification Exam165 Questions
Exam 13: CompTIA Server+66 Questions
Exam 14: CompTIA Server+ Certification Exam779 Questions
Exam 15: CompTIA Security+1 k+ Questions
Exam 16: CompTIA Security+ 2021129 Questions
Exam 17: CompTIA CTT+ Essentials378 Questions
Exam 18: CompTIA Linux+252 Questions
Select questions type
During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager. Which of the following is described in this scenario?
(Multiple Choice)
4.8/5
(27)
A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized.
Which of the following is the NEXT appropriate step for the project manager to take?

(Multiple Choice)
4.8/5
(44)
A company recently went through a project requiring new equipment, new software, and retraining of personnel. This is MOST likely a result of:
(Multiple Choice)
4.8/5
(35)
A stakeholder is unaware of a project's status. Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)
(Multiple Choice)
4.8/5
(47)
Project B cannot start before Project A is complete, but Project B has been given authorization to begin to meet legislative requirements. Which of the following is the BEST way to expedite the projects?
(Multiple Choice)
4.8/5
(34)
One deliverable failed during testing, and this has already happened several times. Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?
(Multiple Choice)
4.8/5
(38)
Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?
(Multiple Choice)
4.9/5
(40)
A project manager is overseeing the construction of a new building. There are likely existing underground water, gas, and electrical lines. Which of the following is an example of mitigation?
(Multiple Choice)
4.7/5
(40)
A project manager is managing a transactional project. One of the key team members is having difficulties understanding the client requirements. Which of the following actions would be BEST for the project manager to take?
(Multiple Choice)
4.8/5
(34)
Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3. Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path?
(Multiple Choice)
4.9/5
(33)
Which of the following would indicate a project manager is working in a matrix-based organization?
(Multiple Choice)
4.8/5
(40)
Which of the following are mutually binding project documents? (Choose two.)
(Multiple Choice)
4.8/5
(44)
Which of the following statements are correct regarding project management? (Choose two.)
(Multiple Choice)
4.8/5
(29)
A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:
(Multiple Choice)
4.8/5
(39)
The following tasks are required to complete an IT project that is behind schedule:
Which of the following is the critical path?

(Multiple Choice)
4.7/5
(40)
The PM has requested that a project repository be developed. Sensitive information will be available on the site that could affect the project's success. Only personnel who need to know the information will have access. Which of the following site types is the PM requesting?
(Multiple Choice)
4.7/5
(32)
A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT?
(Multiple Choice)
4.8/5
(35)
Which of the following is the BEST indicator of project failure?
(Multiple Choice)
4.7/5
(36)
A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project's success. Which of the following risk strategies should the project manager adopt?
(Multiple Choice)
4.7/5
(34)
A project manager is not required to participate in performance appraisal meetings with team members. The project manager is working within which of the following organizational structures?
(Multiple Choice)
4.8/5
(28)