Exam 4: Process Analysis
Exam 1: Using Operations to Compete107 Questions
Exam 2: Project Management151 Questions
Exam 3: Process Strategy149 Questions
Exam 4: Process Analysis192 Questions
Exam 5: Quality and Performance223 Questions
Exam 6: Capacity Planning133 Questions
Exam 7: Constraint Management160 Questions
Exam 8: Lean Systems179 Questions
Exam 9: Supply Chain Inventory Management216 Questions
Exam 10: Supply Chain Design93 Questions
Exam 11: Supply Chain Location Decisions126 Questions
Exam 12: Supply Chain Integration130 Questions
Exam 13: Supply Chain Sustainability and Humanitarian Logistics77 Questions
Exam 14: Forecasting183 Questions
Exam 15: Operations Planning and Scheduling191 Questions
Exam 16: Resource Planning149 Questions
Exam 17: Decision Making118 Questions
Exam 18: Waiting Line127 Questions
Exam 19: Special Inventory Models53 Questions
Exam 20: Linear Programming84 Questions
Exam 21: Simulation61 Questions
Exam 22: Financial Analysis60 Questions
Exam 23: Acceptance Sampling Plans88 Questions
Exam 24: Measuring Output Rates103 Questions
Exam 25: Learning Curve Analysis56 Questions
Exam 26: Operations Scheduling131 Questions
Select questions type
A time study analyst is attempting to determine the standard time for a work element.She observes a worker performing the work element at a higher-than-average pace.How will this fact be reflected in the time standard that is eventually created?
(Multiple Choice)
4.9/5
(32)
The four core processes that merit thorough analysis are supplier relationship,new service/product development,order fulfillment,and service/product recovery.
(True/False)
4.9/5
(36)
The five categories of activities (operation,transportation,inspection,delay,and storage)are used in which of the following methods of process analysis?
(Multiple Choice)
4.9/5
(28)
Scenario 4.3
A job consists of three elements.Twenty observations for each element were timed,and the resulting data are shown in the following table.A performance rating has also been assigned for each element,as shown in the table.The job has an allowance of 15% of normal time.
-Use the information in Scenario 4.3.What is the standard time for the entire job?

(Multiple Choice)
4.8/5
(40)
The first unit of production takes 20 hours to produce and the learning rate is expected to be 90 percent.How long will it take to produce the twelfth unit?
(Multiple Choice)
5.0/5
(40)
An industrial engineer observes a brand new process and develops time standards for several of the manual components of the production line.What are the implications of learning effects on the time standards and the line balance? What could be done to address this situation?
(Essay)
4.8/5
(36)
Scenario 4.4
A job consists of three elements.Twenty observations for each element were timed,and the resulting data are shown in the following table.A performance rating has also been assigned for each element,as shown in the table.The job has an allowance of 20% of normal time.
-Use the information in Scenario 4.4.What is the normal time for job element #1?

(Multiple Choice)
4.7/5
(35)
A professor's graduate assistant can grade a quiz in 40 seconds.Over the course of an academic year he assists with 6 sections of a course with an average of 30 students with 10 quizzes in each section.If he is paid $8 an hour,how much is his annual quiz-grading labor cost to the university?
(Multiple Choice)
4.9/5
(29)
________ involves estimating the proportion of time spent by people and machines on activities,based on a large number of observations.
(Essay)
4.7/5
(28)
The best data analysis tool for representing the mean and standard deviation of a continuous data distribution is a:
(Multiple Choice)
4.8/5
(40)
If a process under analysis is extensive and cuts across several departmental lines,it may benefit from forming a(n):
(Multiple Choice)
4.7/5
(39)
A simulation model goes one step further than possible with analysis tools,because it can show how the process performs ________ over time.
(Essay)
4.9/5
(44)
A restaurant manager tracks complaints from the diner satisfaction cards that are turned in at each table.The data collected from the past week's diners have been plotted and appear in the following graph.The number of complaints for each category is with each bar.
How was the value for the point represented by the triangle calculated?

(Multiple Choice)
4.9/5
(33)
Highly customized job processes and processes that are highly divergent require the use of:
(Multiple Choice)
4.9/5
(37)
Scenario 4.2
Garman observes a worker assembling peanut valves and records the data displayed in the table.
-Use the information in Scenario 4.2.What is the standard time for this job element if the allowance for the process is 20%?

(Multiple Choice)
4.9/5
(37)
Process improvement teams that focus on processes that cut across departmental boundaries have the silo mentality.
(True/False)
4.9/5
(41)
Showing 61 - 80 of 192
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)